Loan and Grant Comparison Tool
Inputs
Assumptions
Rate at which dollar value of benefits is anticipated to
increase
each year as a result of inflation, input range >0
Value must be a number > 0
Rate at which dollar value of construction costs is
anticipated to
increase each year as a result of inflation, input range >0
Value must be a number > 0
Project Information
Most recent cost estimate for design and construction of
project,
input range >0
Value must be a number > 0
Number of years needed to complete design and construction
of
project, input range 1-50
Number of years project will operate without rehabilitation,
input
range 1-50
Estimated annual outlays for O&M, input range >0
Value must be a number > 0
Benefits / costs of project, as calculated by project
sponsor,
input range >0
Value must be a number > 0
Rate used to discount future project cash flows as part of
the BCR
calculation, input range >0
Value must be a number > 0
Percentage of costs planned to be paid for by Federal
appropriations, input range 0%-100%
Value must be a number between 0 and 100
Federal Financing
Percentage of design and construction costs planned to be
financed
through a Federal loan, input range 0%-100%
Value must be a number between 0 and 100
Anticipated interest rate on Federal loan, input range
>0
Value must be a number > 0
Costs associated with underwriting, legal support,
registration
fees and audit fees as % of Federal loan, input range >0
Value must be a number > 0
Number of years loan payments are deferred after
construction is
completed, input range 0-5
Number of years over which the Federal loan is repaid, input
range
1-30
Local Financing
Anticipated interest rate on local loan, input range
>0
Value must be a number > 0
Costs associated with underwriting, legal support,
registration
fees and audit fees as % of local loan, input range >0
Value must be a number > 0
Number of years after start of construction that financing
is
received (typically zero), input range 0-50
Number of years over which the local loan is repaid, input
range
1-30
Rates for Net Present Value (NPV) Evaluation
Local target return on capital (e.g. local borrowing rate),
input range
>0
Value must be a number > 0
Optional - Other return on capital (e.g. Weighted Average
Cost of
Capital), input range >0
Value must be a number > 0
Results
Comparison of Alternatives
Comparison of the project's net present value (benefits
minus
costs) between the two alternative scenarios.
Alternative #1 - 100% Local Equity with Federal Loan for % of Project Costs
Alternative #1 assumes that 100% of the project cost will
eventually be paid by local equity but will initially be financed by a combination
of Federal loan and a local loan (share specified by user inputs).
0.00
0.00
0.00
0.00
0.00
Alternative #2 - % Local Equity with Local
Loan
Alternative #2 assumes that some share of the project cost
(specified by user inputs) will be paid by a grant, and the remaining cost will
be financed through a local loan.
0.00
0.00
0.00
0.00
0.00
Break-Even Analysis
Comparison of the "break-even year" (year in which a loan
becomes less costly than awaiting a grant) using the local hurdle rate as well
as a different user-input discount rate.
Local Hurdle Rate: %
0
0
0
Other User-Defined Discount Rate: %
0
0
0